Skip to main content
 

Street Construction Projects

Keeping a community running smoothly requires the upkeep of Town streets and other road infrastructure. Current and upcoming street construction projects, listed below, show the Town's commitment to a quality network of roads in Riverview.

Project Start Date End Date
Storm & Sanitary Upgrades May 15, 2024 July 10, 2024

MacAllister Park

Replace Underground Wires May 15, 2024 June 30, 2024

Henderson Avenue

New Traffic Signal November 4, 2024 November 30, 2024

Coverdale @ Golf Club Road

Water Main Renewal May 27, 2024 July 31, 2024

Blythwood Avenue

Street Reconstruction June 15, 2024 September 30, 2024

Mitton Road (street reconstruction, culvert) - July 2

Manning Road (street reconstruction, watermain, sewers) - July 29

Sherwood Avenue (street reconstruction, watermain, sewers) - July 29

Suffolk - Strathmore to Crystal (street reconstruction, watermain, sewers) - May 6

Westview Terrace (street reconstruction, watermain, sewers) - July 2

Asphalt Seal May 27, 2024 July 31, 2024

Birkdale Drive

Darwin Drive

Elmore Court

Innwood Court

Ridgeway Drive

Windsor Street

 

Surface mill, Asphalt Overlay & Curb Replacement April 29, 2024 July 31, 2024

Hillsborough Road (Old Coach to Harmony) - Starts April 29, 2024

Wilson Road (Estimated to start May 27, 2024)

Yale Avenue (Estimated to start May 27, 2024)

Runneymeade - Water Tank Epoxy Recoating April 14, 2024 June 18, 2024
Contact
For more information, please contact
Riverview Public Works